Project Update 29 March 2025

With the good weather and low tides this week, Contractors were able to take advantage of the favourable conditions to prepare the new in-water section of the boat ramp. Concrete pours are scheduled to take place in two halves next Monday and Tuesday.

The boat ramp work is expected to be completed by next Friday, 4 April 2025, which should enable it to be reopened while we await the arrival of the pontoon from the supplier. Installation of the pontoon will only take between 1-2 days.