M237-26(T) River Tamar – Bonnie Beach Pontoon – Piling Works
Mariners are advised that piling works will be undertaken at Bonnie Beach Pontoon from Monday, 29 June to Tuesday, 30 June 2026.
During this time, the barge TB Massif will be held in position and manoeuvred using anchors and winch wires. Anchor wires may extend up to 70 metres from the barge but will remain well clear of the navigational channel. Anchors will not be buoyed and are not expected to pose a risk to navigation unless vessels are operating in the immediate vicinity of TB Massif.
TB Massif will maintain a listening watch on VHF Channel 14.
Mariners are requested to exercise caution when transiting the area and keep well clear of TB Massif, anchor wires, mooring lines and associated construction vessels.